● On some projects, especially ones of smaller scope, activity sequencing, activ

● On some projects, especially ones of smaller scope, activity sequencing, activity resource estimating, activity duration estimating, and (70) are so tightly linked that they are viewed as a single process that can be performed by a person over a relatively short period of time.

A.time estimating

B.cost estimating

C.project planning

D.schedule development

正确答案:

D