Schedule development can require the review and revision of duration estimates and resource estimates to create an approved(74)that can serve as a baseline to track progress. A.scope statement B.activity list C.project charter D.project schedule

正确答案:

D制定进度表可能要求对历时估算与资源估算进行审查与修改,以便进度表在批准之后能够当做跟踪项目绩效的基准使用。