● The project schedule is more than a document that lays out the activities over
● The project schedule is more than a document that lays out the activities over time to represent the time dimension of the project, it is a management tool to be used for decision making. As such, the schedule is used by the project management team to (73) .
(73)
A. measure, delay, record, distribute, analyze, and direct
B. plan, schedule, monitor, control, report, and forecast
C. promote, highlight, monitor, control, forecast, and report
D. emphasize, visualize, analyze, conceptualize, report, and record
正确答案:B