is the budgeted amount for the work actually completed on the schedule activity
is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.
A.Planned value
B.Earned value
C.Actual cost
D.Cost variance
正确答案:B解析:挣值是在给定时期内按进度活动或WBS部件所完成工作的预算值。
词条内容仅供参考,如果您需要解决具体问题
(尤其在法律、医学等领域),建议您咨询相关领域专业人士。
