万能百科  > 所属分类  > 

is the budgeted amount for the work actually completed on the schedule activity

is the budgeted amount for the work actually completed on the schedule activity or WBS component during a given time period.

A.Planned value

B.Earned value

C.Actual cost

D.Cost variance

正确答案:

B解析:挣值是在给定时期内按进度活动或WBS部件所完成工作的预算值。