The Estimate Activity Resource process is closely coordinated with the(73) proce

The Estimate Activity Resource process is closely coordinated with the(73) process.

A.Estimate Costs

B.Sequence Activities

C.Plan Communications

D.Conduct Procurements

正确答案:

A解析:估算活动资源与成本估算是密切联系的。