The Estimate Activity Resource process is closely coordinated with the(73) proce
The Estimate Activity Resource process is closely coordinated with the(73) process.
A.Estimate Costs
B.Sequence Activities
C.Plan Communications
D.Conduct Procurements
正确答案:A解析:估算活动资源与成本估算是密切联系的。
词条内容仅供参考,如果您需要解决具体问题
(尤其在法律、医学等领域),建议您咨询相关领域专业人士。
