● Project work packages are typically decomposed into smaller components called
● Project work packages are typically decomposed into smaller components called activities to provide a basis for (72), scheduling, executing, and monitoring and controlling the project work.
(72)
A. reviewing
B. estimating
C. auditing
D. expecting
正确答案:B