● Changes may be requested by any stakeholder involved with the project, but cha

● Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by (73).

(73)

A.executive IT manager

B.project manger

C.change control board

D.project sponsor

正确答案:

C试题(73)分析项目变更可以由IT经理executive IT manager、项目管理者project manager、项目发起人project sponsor等任意项目干系人发起,但只有变更控制委员会change control board授权通过,所以选C。参考答案(73)C